Bush IAH Taxiways, TX

Houston, Texas

  • 600
    days

    Time period

  • $
    42
    M

    Cost

Bush Intercontinental Airport project was to refurbish and construct Taxiways WA – WB and new west vault.

Bush Intercontinental Airport project was to refurbish and construct Taxiways WA – WB and new west vault.

Work included subgrade and concrete pavement demolition / removal, subgrade stabilization and repaving of taxiways, as well as new taxiway construction and total replacement and upgrade to electrical systems and construction of a new FAA communications vault.

The $42 million project was completed in eight phases over 600 days. All milestones were met with work completed in March 2012.