  • 18
    Months

  • 23
    .4 M$

The Bush Intercontinental Airport Automated People-mover between Terminals A and B required extensive coordination with airport operations. Webber constructed the people mover’s foundations superstructure and train deck.

Completed in March 2010, the $23.4 million project featured tight working conditions throughout its 18-month duration. Close partnering between Webber’s workforce, the airport, and airlines was essential since the people mover was built while keeping the terminals and adjacent parking garage open at all times.